Build a quote-ready fibre bill of quantities that covers cable, closures, termination, patching, protection, consumables, testing and documented handover.
Turn the site route into measurable segments
Start with a route drawing or schedule rather than a product list. Divide the network into segments between cabinets, closures, poles, buildings, handholes or equipment locations. Record measured or estimated length, installation environment, entry method, available pathway and required service slack for each segment. State whether a route is indoor, outdoor, duct, aerial, direct-buried or mixed, and identify transitions between environments. This establishes cable construction and installation hardware before quantities are guessed. Add a clear allowance policy instead of silently increasing every length by an arbitrary percentage.
- Segment start and end points
- Measured route length and approved allowance
- Indoor, duct, aerial or other environment
- Pulling access and cable-entry constraints
- Required fibre count and spare capacity
Define the optical architecture
Record whether each link is point-to-point or part of a passive optical network. Identify single-mode or multimode fibre, the active equipment interfaces, wavelengths where relevant and the planned connector or splice arrangement. For a passive network, list every splitter ratio and location. Build a loss budget containing fibre, mated connections, splices and splitters, then compare it with the equipment power budget and design margin. A BOQ that lists cable and splitters without showing how they form a link is difficult to verify and easy to under-specify.
Count termination and protection hardware
For every cable end and intermediate joint, define the enclosure, gland or entry kit, splice tray capacity, pigtails, adapters, patch-panel ports and patch leads. Match connector body, polish and fibre type. Include dome joints or distribution boxes with enough entries and usable tray capacity for the cable construction and planned splices. Add labels, blanking pieces, mounting hardware and cabinet-management components. Check that an outdoor enclosure and its cable seals suit the installation method rather than assuming an IP label alone answers every mechanical requirement.
Add tools, consumables and testing
Projects often stop for small items that never appeared on the equipment list. Include splice protectors, approved cleaning materials, wipes, disposal containers, labels, pulling materials and other installation consumables. Identify whether the team supplies the fusion splicer, cleaver, inspection scope, optical loss test set, VFL and OTDR. Specify required calibration and test formats where the customer expects formal acceptance. Test cords, launch fibres and connector adapters must match the link under test. Testing effort and documentation should be priced rather than treated as an unrecorded extra.
- Cleaning and inspection materials
- Splice sleeves and trays
- Labelling and route identification
- Source/power-meter and OTDR accessories
- Test reports, as-built drawings and handover files
Send assumptions with the RFQ
A useful RFQ distinguishes confirmed quantities from allowances and unknowns. Include drawings, equipment schedules, required dates, delivery stages and approved alternatives. State who supplies cabinets, power, civils, access equipment and active optics. If ATTAC is asked only to supply materials, the installer or designer remains responsible for final quantities and suitability. ATTAC can review the product schedule for obvious compatibility gaps and quote available alternatives when the context is supplied. Revise the BOQ after the site survey instead of allowing preliminary quantities to become the uncontrolled purchase list. Give revisions a date and version so purchasing does not combine superseded quantities with the final design.
Give every line item a reason: route, termination point, protection requirement, spare policy, tool activity or handover deliverable.
Need products for this topic?
ATTAC can help match parts, quantities and alternatives.
Common questions
Can ATTAC quote from a preliminary BOQ?
Yes. Mark estimated lengths, unknown connector details and acceptable alternatives clearly so the quote does not imply that preliminary assumptions have been technically approved.
Should spare fibre and spare cable be included?
Use a documented project policy for spare fibres, service loops and stock. The amount depends on route risk, repair strategy, cable construction and customer requirements.
What test deliverables should appear in the BOQ?
Name the required test method, wavelengths, link identification, pass criteria and report format, plus any OTDR traces, inspection records and as-built documentation required by the customer.
Technical references
Authoritative background used to check the technical guidance in this resource.
Related category
Cabinets, Enclosures & Boxes
Cabinets, enclosures, patch panels and accessories for organised network and fibre installations.
Related category
Fibre Optic Products
Fibre cable, patch leads, connectors, adapters, splitters, closures and installation accessories for fibre projects.
FSM
A-81S Fusion Splice Machine
A-81S fusion splice machine for optical fibre cable projects, supplied as a 1 kit set with 41 x 31 x 22.5 cm dimensions and 6 kg weight.
KD144-9
144 Core Heatshrink Dome Joint with 9 Inlets
144 core heatshrink fibre dome joint with 9 inlets for aerial, duct, direct burial and wall-mounted fibre installations.
KP12OM3
12 Port Fibre Patch Panel Populated OM3
12 port populated OM3 fibre patch panel for fibre patching and distribution installations.